The end of July saw all earthworks completed.
The disabled bathroom, septic tank and drainage is fully completed, is operational and has been passed by Council.
We now have in place all fixed target frames for both the 50m and 100yd lines and target bases have been fixed down in position, ready to install the fixed backers.
Saturday 15th August will see the last four bench tops completed and the 200yd line poured (weather permitting). Once this is all in place, we will be commencing with framing up the 300yd line, ready to pour concrete for it.
Stay tuned for more updates and photos in a couple of weeks!!
Thank you!
Colo Benchrest Shooting Club
Cant wait for the first post-covid match!
Rob.
BB Administrator
great progress there with the target frame holders in it’s all starting to take shape I cant weight to see the frame work for the moving backers and stationary one in place good work all it’s looking good cheers
WALLY