Hi All,
Last Friday saw the 200yd line poured along with the last 4 concrete bench tops.
Target bases were bolted in place on Saturday.
The 200yd target backers will be installed on 22/8/2020 and bench tops put in place meaning that ALL of the firing line will be completed along with the Office, Amenities, Loading Shed and Kitchen.
Only the 300yd target line to go and then it is up to FAR!
We will update again shortly with more photos to come so stay tuned!!
Thank you
Colo Benchrest Shooting Club